HS2

Our project works included the installation of all Drainage systems, separators, head walls, lagoons, ditches.

The 3 projects On Hs2 were for the site compound at West Street, School hill batching plant and the 6 mile link road from Station road to west street compound.

In total an all 3 projects we installed over 8 miles of drainage during a period of 18 months including 4 Separators and 192 manholes.

All drainage installations were checked by an independent Inspection company employed by the client before works would be signed off as completed.

The project took 18 Months to complete and 75,000-man hours, in total 115,200m3 of earth was excavated and over 8 miles of drainage installed.

The project was a complete success with 0 accident or Incidents.

Other Projects
View some of our other projects!
Vincent McMorrow
Director
07768387823
James Tubman
Contracts Director
07539322806
Jim McCarney
Office Manager
07971831789
Darina McMorrow
Office Administrator
07572751887
Ken Mubiru
Project Manager
07901023574

Let’s work together

If you have any questions, please do not hestitate to get in touch using the contact form below!
crossmenu